Free Excel format

Rooftop solar project tracker in Excel

One row per project from enquiry to subsidy, with the days at the current stage. A project stuck for over 15 days turns red.

Download the Excel file.xlsx · 51 KB · 18 columns · no form, no email

What the file looks like

The heading row and the five example rows, as they open in Excel. Under them the file has empty rows that are ready: the lists, the formulas and the colours are already set.

Sheet: Projects18 columns
Project no.CustomerPhoneAddressDISCOMConsumer no.Size (kW)StageStage startedDays at this stageWaiting onOur personApplication no.Order valueReceivedBalanceNext action dateRemarks
S-041Deepak Chaudhary98xxx 20714Sector 11, RohtakState DISCOM2841xxxx065Inspection and net meter21 Sept 2026fills itselfDISCOMManojAPP-41xxx72,85,0002,28,000fills itself10 Oct 2026Visited the SDO office. File is with the JE.
S-044Anita Rastogi97xxx 66310Model Town, PanipatState DISCOM5120xxxx913Portal application4 Oct 2026fills itselfPortalManojAPP-44xxx21,74,00052,000fills itself12 Oct 2026Applied. Waiting for feasibility.
S-046Rakesh Tyagi99xxx 05582Shastri Nagar, MeerutState DISCOM7733xxxx184Order1 Oct 2026fills itselfCustomerSeema2,32,00046,000fills itself9 Oct 2026Property paper still to come.
S-038Sarita Verma98xxx 91027Vasundhara, GhaziabadState DISCOM6405xxxx473Subsidy claim16 Sept 2026fills itselfPortalSeemaAPP-38xxx51,71,0001,71,000fills itself13 Oct 2026Claim raised. Bank details verified.
S-047Mohit Chauhan96xxx 43390Sector 4, KarnalState DISCOM6Site survey8 Oct 2026fills itselfSurvey teamManojfills itself11 Oct 2026Survey on Saturday morning.
Example rows with invented names. On a phone, slide the sheet sideways to see every column.
  • Red row: More than 15 days at one stage. (Change 15 to your own limit in Home, Conditional Formatting, Manage Rules.)
  • Amber row: The next action is due today or was missed.
  • Green row: Handed over.

The columns, and what to write in each

  1. Project no.

    Your own running number: S-041.

  2. Customer

    Name as on the electricity bill.

  3. Phone

    Mobile number.

  4. Address

    Area and city.

  5. DISCOM

    The supply company.

  6. Consumer no.

    From the electricity bill.

  7. Size (kW)

    Proposed or installed size.

  8. Stage

    One current stage.

    EnquirySite surveyQuoteOrderPortal applicationApprovalInstallationInspection and net meterSubsidy claimHandover
  9. Stage started

    The day the project reached this stage.

  10. Days at this stage

    Fills itself: today minus the day the stage started.

  11. Waiting on

    Who has the ball.

    SalesSurvey teamCustomerPortalDISCOMOur team
  12. Our person

    One name from your team, at every stage.

  13. Application no.

    From the portal.

  14. Order value

    Agreed price.

  15. Received

    Money received so far.

  16. Balance

    Fills itself: order value minus received.

  17. Next action date

    When someone looks at this project next.

  18. Remarks

    What was said at the office, what paper is missing.

How to keep it

  1. Give every project a number on the day of the enquiry and use it in every chat and on every document.
  2. When a project moves, change "Stage" and write today's date in "Stage started". "Days at this stage" counts by itself.
  3. Keep one person of your own team against every project, even when the ball is with the DISCOM.
  4. Type application numbers and meter numbers into the row. They must not stay in a photo on a phone.
  5. Once a week, sort by "Days at this stage", longest first, and read the red rows together.
Take the rooftop solar project tracker with you

Free to use and to change. No macros, nothing to install.

Download the Excel file
The guide behind this format

How to track rooftop solar projects from enquiry to subsidy

The usual stages of a rooftop solar job, what to record at each one, payment wording for the quote, and a weekly review that shows which file is stuck.

4 min read

People also look for this as: solar project tracking sheet in Excel · rooftop solar project tracker · solar installation tracker

When the sheet stops being enough

A sheet works while one or two people keep it. When staff must update from the godown or the road, and reminders must go out by themselves, the same columns become a system. Try it in your browser, without a sign-up.

Solar Project Tracker: a sample screen of the system

Solar Project Tracker

Projects & Service

Survey, application, installation, net meter and subsidy on one board. Stuck files turn red, papers are ticked, and customers get updates on WhatsApp.

Try the demoFrom ₹25,000Open →
Questions
Is this rooftop solar project tracker format free?+

Yes. The download starts at once: no form, no email and no sign-up. Use it and change it for your own business.

Does the file have macros?+

No. It is a plain .xlsx file with dropdown lists, a few formulas and colour rules. There is nothing to install and nothing to switch on.

Why do the example rows show dates around today?+

The five example rows carry dates that move with today, so a file opened next month still shows how a late row looks. Type over the examples or delete them before you start.

Which program do I need to open it?+

It was made for Microsoft Excel on a computer and checked there. Other spreadsheet programs open .xlsx files too, but we have not checked the dropdown lists and the colours in each of them.

Can I change the columns?+

Yes. Rename a column, add your own, or change the choices of a dropdown list (Data, then Data Validation). The "How to use" sheet says what each column is for.